first_imgAugust 26, 2009 This report continues from 8/24. Here we see the pour of the heat duct tunnel wall in full swing. The construction crew laid a bridge on the scaffolding to facilitate the workers and equipment during the course of the pouring process. Many people came from different departments to help with the pour. [photo & text: Anna Tran] The mixed concrete was placed into wheelbarrows and buckets and shuttled down to the scaffolding to be poured into the formwork. Here we see the entire work in process. [photo & text: Anna Tran] The crew disassembled the wall forms after the concrete cured. The next section of the wall will be under way with erection of the formwork and we will continue to report on this next week. [photo & text: Anna Tran]last_img